Russell, MN

Russell Infrastructure Improvement Project Project Overview / Objectives Construction for Phase 1 the City of Russell’s Infrastructure Improvements Project began May 2024. The locations of activities associated with Phase 1 of the project are shown on the map and the work to be completed consists of replacement of watermains, sanitary and storm sewers, lift stations, […]
Lake Lillian, MN

Lake Lillian Infrastructure Improvement Project Project Updates 7/23/25 The project is wrapping up! Final seeding is taking place, and miscellaneous cleanup work will continue as needed. Thank you for your patience throughout construction. 5/6/25 All underground work has been completed. The Contractors are working on concrete curb and gutter, driveways and sidewalk. Paving is being […]
Thomson Township

Thomson Township Randall Avenue Sewer Extension Project Updates The project is scheduled to begin June of 2025. 6/22/25 Through the first two weeks of June, the Township’s contractor, Veit, constructed the sewer mains up Randall Avenue. Each home received a stub to connect to, and some homeowers have already made their connections. The next steps […]
Hector Municipal Airport Runway Construction

Hector Municipal Airport Runway, Lighting NAVAIDs Construction Project Updates Stay tuned for project updates! 8/18/26 DATE CHANGE: The Hector Lion’s Fly-In breakfast will be on Sunday September 13, 2026. If you want to learn more about the runway reconstruction project, be sure to visit the Bollig table at the Fly-In! 7/1/26 The Hector Lion’s Fly-In […]
Okabena Water Tower

Okabena, MN Water Tower Project Project Updates View the latest Okabena water tower project updates below. 8/12/26 The water tower project is complete and the tower is back in operation. 7/9/26 The structural repairs, blasting, and painting of the water tower have been completed. The contractor is working on cleaning up material around the project […]
Okabena Infrastructure Improvements

Okabena, MN Infrastructure Improvements Project Updates Project updates about the Okabena Infrastructure Improvements project will be added here. 8/12/26 Storm Sewer, watermain, and sanitary around the school has been installed. Street reconstruction has started with cement stabilized soil operation starting on 8/19/2026. The contractor is working to restore the streets to gravel around the school. […]
Lamberton Grove Street Infrastructure Improvements

Lamberton, MN Grove Street Project Updates Check out the latest updates about this project below. 8/06/26 Sanitary sewer installation is very nearly complete, drinking water main and services installation is also nearing completion. Work on removing the reclaimed roadway material is moving from south to north, into the 400 and 300 blocks very soon. Street […]
Tracy, MN – Phase E Infrastructure Improvements

Tracy, MN Infrastructure Improvements Phase E Project Updates Check out the latest project updates below. 8/18/26 Contractors have been working to move a gas main along 1st St E between Elm St and Hollett St. Tree removal for the project has started and will be completed the week of 8/17. Resident flyers were mailed out […]
Wood Lake Infrastructure Improvements Phase 3

Wood Lake, MN Infrastructure Improvements Phase 3 Project Updates 8/17/26 Construction is currently underway. Stay tuned for future updates! Project Overview / Objectives Wood Lake’s infrastructure improvements consists of replacement of watermains, sanitary and storm sewers, and the repaving of affected roadways. The map below shows areas that will be directly affected by construction activities. […]