Russell, MN

Russell Water Tower

Russell Infrastructure Improvement Project Project Overview / Objectives Construction for Phase 1 the City of Russell’s Infrastructure Improvements Project began May 2024. The locations of activities associated with Phase 1 of the project are shown on the map and the work to be completed consists of replacement of watermains, sanitary and storm sewers, lift stations, […]

Lake Lillian, MN

Lake Lillian Project

Lake Lillian Infrastructure Improvement Project Project Updates 7/23/25 The project is wrapping up! Final seeding is taking place, and miscellaneous cleanup work will continue as needed. Thank you for your patience throughout construction. 5/6/25 All underground work has been completed. The Contractors are working on concrete curb and gutter, driveways and sidewalk.  Paving is being […]

Thomson Township

Thomson Township Randall Avenue Sewer Extension  Project Updates The project is scheduled to begin June of 2025.  6/22/25 Through the first two weeks of June, the Township’s contractor, Veit, constructed the sewer mains up Randall Avenue. Each home received a stub to connect to, and some homeowers have already made their connections. The next steps […]

Hector Municipal Airport Runway Construction

Hector Municipal Airport Runway, Lighting NAVAIDs Construction Project Updates Stay tuned for project updates! 9/17/26 The airport runways are scheduled to be closed starting on Monday, Oct 5th.  Please note that the runway is expected to be closed until July 2027. If your aircraft will need to be moved into or out of the hangar […]

Okabena Water Tower

Okabena, MN Water Tower Project Project Updates View the latest Okabena water tower project updates below. 8/12/26 The water tower project is complete and the tower is back in operation. 7/9/26 The structural repairs, blasting, and painting of the water tower have been completed. The contractor is working on cleaning up material around the project […]

Okabena Infrastructure Improvements

Okabena, MN Infrastructure Improvements Project Updates Project updates about the Okabena Infrastructure Improvements project will be added here. 9/9/26 The installation of the underground utilities is nearly completed. Concrete has been placed around the school, and the first round of paving has been completed. The rest of the underground utility work is scheduled for the […]

Lamberton Grove Street Infrastructure Improvements

Lamberton, MN Grove Street Project Updates Check out the latest updates about this project below. 9/4/26 Underground water and sewer construction is complete. Upcoming work for September includes excavating street areas, installing geotextile, and placing, shaping, and compacting aggregate base materials. It is anticipated that remaining concrete driveway removals and installation of new driveway aprons […]

Tracy, MN – Phase E Infrastructure Improvements

Tracy Infrastructure Phase E Project - Bollig Engineering

Tracy, MN Infrastructure Improvements Phase E Project Updates Check out the latest project updates below. 9/16/26 Construction has started on the Phase E project. Tree removal throughout the project area has been completed. Removals along North St. and 1st St E between E Hollett St and North St have been completed. Removals included pavement along […]

Wood Lake Infrastructure Improvements Phase 3

Wood Lake, MN Infrastructure Improvements Phase 3 Project Updates 9/02/26 Work on the street and utility improvements continued steadily over the past month. Recent construction activities included: Removal of the existing pavement along project streets. Installation of approximately 440 feet of new 24-inch storm sewer along 1st Street and 5th Avenue. Installation of approximately 340 […]

en_USEnglish