Russell, MN

Russell Infrastructure Improvement Project Project Overview / Objectives Construction for Phase 1 the City of Russell’s Infrastructure Improvements Project began May 2024. The locations of activities associated with Phase 1 of the project are shown on the map and the work to be completed consists of replacement of watermains, sanitary and storm sewers, lift stations, […]
Lake Lillian, MN

Lake Lillian Infrastructure Improvement Project Project Updates 7/23/25 The project is wrapping up! Final seeding is taking place, and miscellaneous cleanup work will continue as needed. Thank you for your patience throughout construction. 5/6/25 All underground work has been completed. The Contractors are working on concrete curb and gutter, driveways and sidewalk. Paving is being […]
South Haven, MN

South Haven Infrastructure Improvement Project Project Updates Phase 2 of the project in South Haven will start in the Spring of 2025. 7/23/25 The project is wrapping up! Final seeding is taking place, and miscellaneous cleanup work will continue as needed. Thank you for your patience throughout construction. 6/4/25 Seeding and cleanup will be finished […]
Thomson Township

Thomson Township Randall Avenue Sewer Extension Project Updates The project is scheduled to begin June of 2025. 6/22/25 Through the first two weeks of June, the Township’s contractor, Veit, constructed the sewer mains up Randall Avenue. Each home received a stub to connect to, and some homeowers have already made their connections. The next steps […]
Okabena Infrastructure Improvements

Okabena, MN Infrastructure Improvements Project Updates Project updates about the Okabena Infrastructure Improvements project will be added here. 6/10/26 Sanitary is 90% complete. Reclaim of the streets has been completed. The lift station building rehabilitation has been completed. Directional drilling of the watermain is scheduled for end of June. 6/4/26 Water will be temporarily shut […]
Okabena Water Tower

Okabena, MN Water Tower Project Project Updates View the latest Okabena water tower project updates below. 6/10/26 Welding repairs are completed and sandblasting is nearly complete. Upcoming work includes finishing blasting on the interior wet, finishing blasting on the exterior dry, and painting. 6/2/26 The welding repairs are mostly complete. The contractor is working on […]
Hector Municipal Airport Runway Construction

Hector Municipal Airport Runway Construction Project Updates Stay tuned for project updates when this project gets started 7/1/26 The Hector Lion’s Fly-In breakfast is coming up on September 20, 2026! Airport construction will start after the event. Project Overview / Objectives Construction for Hector Municipal Airport’s Runway Reconstruction and Visual Aids Project will begin in […]
Tracy, MN – Phase E Infrastructure Improvements

Tracy, MN Infrastructure Improvements Phase E Project Updates Stay tuned for future updates! 6/16/26 This project is scheduled to start in August, 2026. Stay tuned for future project updates! Project Overview / Objectives Tracy’s infrastructure improvements consists of replacement of watermains, sanitary and storm sewers, and the repaving of affected roadways. Work will […]
Lamberton Grove Street Infrastructure Improvements

Lamberton, MN Grove Street Project Updates Check out the latest updates about this project below. 6/30/26 Construction is expected to begin the week of July 6, with tree removal starting on Monday and asphalt pavement reclamation (grinding up the street pavement into gravel) planned to begin on Thursday. Please plan to have no vehicles parked […]