Russell, MN

Russell Infrastructure Improvement Project Project Overview / Objectives Construction for Phase 1 the City of Russell’s Infrastructure Improvements Project began May 2024. The locations of activities associated with Phase 1 of the project are shown on the map and the work to be completed consists of replacement of watermains, sanitary and storm sewers, lift stations, […]
Lake Lillian, MN

Lake Lillian Infrastructure Improvement Project Project Updates 7/23/25 The project is wrapping up! Final seeding is taking place, and miscellaneous cleanup work will continue as needed. Thank you for your patience throughout construction. 5/6/25 All underground work has been completed. The Contractors are working on concrete curb and gutter, driveways and sidewalk. Paving is being […]
Thomson Township

Thomson Township Randall Avenue Sewer Extension Project Updates The project is scheduled to begin June of 2025. 6/22/25 Through the first two weeks of June, the Township’s contractor, Veit, constructed the sewer mains up Randall Avenue. Each home received a stub to connect to, and some homeowers have already made their connections. The next steps […]
Hector Municipal Airport Runway Construction

Hector Municipal Airport Runway Lighting, NAVAIDs Construction Project Updates Please see the project updates below: 10/19/26 Runway reclamation is complete, and crews are now grading and widening the new runway. Trucks are hauling material across Highway 4 to various locations on the project site. Grading work is expected to continue over the next couple of […]
Okabena Water Tower

Okabena, MN Water Tower Project Project Updates View the latest Okabena water tower project updates below. 8/12/26 The water tower project is complete and the tower is back in operation. 7/9/26 The structural repairs, blasting, and painting of the water tower have been completed. The contractor is working on cleaning up material around the project […]
Okabena Infrastructure Improvements

Okabena, MN Infrastructure Improvements Project Updates Project updates about the Okabena Infrastructure Improvements project will be added here. 10/19/26 Okabena’s infrastructure improvements project continues with crews paving several streets in September and completing additional water service line installations. Rain and scheduling changes slowed work during mid-September, but crews are back in town finishing up the […]
Lamberton Grove Street Infrastructure Improvements

Lamberton, MN Grove Street Project Updates Check out the latest updates about this project below. 10/7/26 Concrete work is nearing completion. The Contractor plans to place black dirt behind curbs and adjacent to driveways and sidewalks starting the week of 10/12. Grass seeding schedule is TBD and weather-dependent; seed will either be placed yet this […]
Tracy, MN – Phase E Infrastructure Improvements

Tracy, MN Infrastructure Improvements Phase E Project Updates Check out the latest project updates below. 10/26/26 Crews installed sanitary sewer mains, manholes, and water and sewer service connections serving residents along North St. New water main along First Street East was connected to the existing system at Hollett Street. Pavement edge drains were installed along […]
Wood Lake Infrastructure Improvements Phase 3

Wood Lake, MN Infrastructure Improvements Phase 3 Project Updates 10/22/26 Utility Installation Progress Watermain: Approximately 95% complete Sanitary Sewer: 100% complete Storm Sewer: Approximately 60% complete, with the remaining installation beginning this week and continuing into next week Roadway Progress Roadway preparation has advanced substantially throughout the project area. With the exception of 2nd Street […]