Okabena Water Tower

Okabena, MN Water Tower Project Project Updates Project updates about the Okabena water tower project will be added here. 4/20/26 The contractor started construction on April 13th. The sanitary sewer is installed along Honeysuckle Ln. The contractor will begin construction of the sanitary sewer along Elevator Dr. this week. Project Overview / Objectives Construction for […]
Okabena Infrastructure Improvements

Okabena, MN Infrastructure Improvements Project Updates Project updates about the Okabena Infrastructure Improvements project will be added here. 4/20/26 The contractor started construction on April 13th. The sanitary sewer is installed along Honeysuckle Ln. The contractor will begin construction of the sanitary sewer along Elevator Dr. this week. Project Overview / Objectives Construction for the […]
Thomson Township

Thomson Township Randall Avenue Sewer Extension Project Updates The project is scheduled to begin June of 2025. 6/22/25 Through the first two weeks of June, the Township’s contractor, Veit, constructed the sewer mains up Randall Avenue. Each home received a stub to connect to, and some homeowers have already made their connections. The next steps […]
South Haven, MN

South Haven Infrastructure Improvement Project Project Updates Phase 2 of the project in South Haven will start in the Spring of 2025. 7/23/25 The project is wrapping up! Final seeding is taking place, and miscellaneous cleanup work will continue as needed. Thank you for your patience throughout construction. 6/4/25 Seeding and cleanup will be finished […]
Lake Lillian, MN

Lake Lillian Infrastructure Improvement Project Project Updates 7/23/25 The project is wrapping up! Final seeding is taking place, and miscellaneous cleanup work will continue as needed. Thank you for your patience throughout construction. 5/6/25 All underground work has been completed. The Contractors are working on concrete curb and gutter, driveways and sidewalk. Paving is being […]
Russell, MN

Russell Infrastructure Improvement Project Project Overview / Objectives Construction for Phase 1 the City of Russell’s Infrastructure Improvements Project began May 2024. The locations of activities associated with Phase 1 of the project are shown on the map and the work to be completed consists of replacement of watermains, sanitary and storm sewers, lift stations, […]