Thomson Township

Thomson Township Randall Avenue Sewer Extension  Project Updates The project is scheduled to begin June of 2025.  6/22/25 Through the first two weeks of June, the Township’s contractor, Veit, constructed the sewer mains up Randall Avenue. Each home received a stub to connect to, and some homeowers have already made their connections. The next steps […]

South Haven, MN

South Haven Infrastructure Project - Bollig Engineering

South Haven Infrastructure Improvement Project Project Updates Phase 2 of the project in South Haven will start in the Spring of 2025.  7/23/25 The project is wrapping up! Final seeding is taking place, and miscellaneous cleanup work will continue as needed. Thank you for your patience throughout construction. 6/4/25 Seeding and cleanup will be finished […]

Lake Lillian, MN

Lake Lillian Project

Lake Lillian Infrastructure Improvement Project Project Updates 7/23/25 The project is wrapping up! Final seeding is taking place, and miscellaneous cleanup work will continue as needed. Thank you for your patience throughout construction. 5/6/25 All underground work has been completed. The Contractors are working on concrete curb and gutter, driveways and sidewalk.  Paving is being […]

Russell, MN

Russell Water Tower

Russell Infrastructure Improvement Project Project Overview / Objectives Construction for Phase 1 the City of Russell’s Infrastructure Improvements Project began May 2024. The locations of activities associated with Phase 1 of the project are shown on the map and the work to be completed consists of replacement of watermains, sanitary and storm sewers, lift stations, […]

en_USEnglish