Thomson Township

Randall Avenue Sewer Extension 

Project Updates

The project is scheduled to begin June of 2025. 

Through the first two weeks of June, the Township’s contractor, Veit, constructed the sewer mains up Randall Avenue. Each home received a stub to connect to, and some homeowers have already made their connections.

The next steps are to continue to install the sand and gravel sub-road support; and ultimately pave the road this year. Currently the road is sitting and settling before completing the project. Bollig and the Township will be periodically checking in on the road status until construction resumes.

All homes have access to Maple Drive and Flynn Street. If you have any concerns, please don’t hesitate to reach out to us.

The project is scheduled to begin June of 2025.

Project Overview / Objectives

Construction for the sewer extension along Randall Avenue is set to begin early summer. The locations of activities associated with this project are shown on the attached map and the work to be completed consists of installing sanitary sewer and then repaving Randall Avenue. The project is scheduled to take place from summer to fall of 2025, with the final lift of pavement and cleanup into the fall of 2025.

There are no utility disruptions anticipated with this project. 

Anticipated Schedule

The following is a summary of the preliminary project schedule:

  • June 2025: Start of Construction
  • September 2025: Substantial Completion
  • October 2025: Final Completion

During construction, there will be some additional heavy truck and equipment traffic coming through town. It will be necessary to close streets partially or completely to vehicular traffic for your safety. Street parking may also be restricted at some times and in certain areas.

Resident Resources

The Township, Contractors, and Bollig Engineering ask that everyone stay clear of construction zones, obey construction signs, and be safe and cautious around construction equipment. If you have questions or concerns about the project, please contact Will O’Halloran, on-site Resident Project Representative (RPR) or Nathan Feist, Project Engineer at 218.595.7940. 

Project Progress

Thomson MN Construction Update - Bollig Engineering

Will O’Halloran
Resident Project Representative

Bollig Engineering
wohalloran@bollig-engineering.com
218-595-7940

Nathan Feist
Project Engineer

Bollig Engineering
nfeist@bollig-engineering.com
218-595-7940

Veit Construction
veitusa.com
218-626-2242

en_USEnglish